top of page

Park District, Illinois

Parks & Recreation

Rooftop Solar PV

159kW

System Size

--

Gas Equiv. Eliminated

174,521

kWh/Year

--

Load Offset %

122 tons

CO2 Offset/yr

CapEx

Finance Model

GEC Role: EPC

When the utility's grid infrastructure made the planned three-phase inverter system cost-prohibitive, GEC redesigned the 159 kW installation around single-phase inverters — distributing power generation across additional units to maintain full system efficiency. The solution delivered the same output while avoiding a costly transformer upgrade.

Schedule Your Site Assessment