Park District, Illinois
Parks & Recreation
•
Rooftop Solar PV
159kW
System Size
--
Gas Equiv. Eliminated
174,521
kWh/Year
--
Load Offset %
122 tons
CO2 Offset/yr
CapEx
Finance Model
GEC Role: EPC
When the utility's grid infrastructure made the planned three-phase inverter system cost-prohibitive, GEC redesigned the 159 kW installation around single-phase inverters — distributing power generation across additional units to maintain full system efficiency. The solution delivered the same output while avoiding a costly transformer upgrade.