Moving & Storage Company Ph 2 —201kW
Rooftop Solar PV
System Size
201kW
System Size
23,297
Gas Equiv. Eliminated
234,904
kWh/Year
75
Load Offset %
207 tons
CO2 Offset/yr
CapEx
Finance Model
GEC Role: Developer & EPC
A second installation for this moving and storage operator required GEC to resolve a significant infrastructure challenge: the existing transformer was insufficient for the solar system's grid connection requirements. GEC coordinated the utility-mandated upgrade from engineering through approval, delivering a 201 kW system generating 235,000 kWh annually.