top of page

Moving & Storage Company Ph 2 —201kW

Rooftop Solar PV

System Size

201kW

System Size

23,297

Gas Equiv. Eliminated

234,904

kWh/Year

75

Load Offset %

207 tons

CO2 Offset/yr

CapEx

Finance Model

GEC Role: Developer & EPC

A second installation for this moving and storage operator required GEC to resolve a significant infrastructure challenge: the existing transformer was insufficient for the solar system's grid connection requirements. GEC coordinated the utility-mandated upgrade from engineering through approval, delivering a 201 kW system generating 235,000 kWh annually.

Schedule Your Site Assessment
bottom of page